Billions Without a Tender: What is Happening with the Military Cemetery Construction in the Neighboring Community
An additional UAH 879 million has been allocated without an open tender for the first stage of the National Military Memorial Cemetery in the Hatne community of Fastiv district.
Key points
- UAH 879 million allocated without a tender
- Contractor is the Building UA consortium
- First-stage cost rose to UAH 3.02 billion
- Facility located in Hatne community of Fastiv district
The construction of the National Military Memorial Cemetery, being built in the Markhalivka forest within the Hatne community of Fastiv district, continues to attract public attention. Despite changes in leadership across relevant government bodies, the project is being implemented using previous contract coordination schemes. Specifically, a state institution signed an additional agreement worth UAH 879.02 million with the same general contractor, the Building UA consortium.
It is important to note that this large-scale contract was concluded without holding open competitive tenders. Due to amendments in the project documentation and additional expert reviews, the total cost of constructing the first stage of the memorial complex has risen to a record UAH 3.02 billion. As of the time the agreement was signed, builders had already utilized over UAH 857 million of previously allocated funds.
What Has Changed in the Project and What Works are Planned
Following the adjustment of initial plans, the state institution and the contractor significantly expanded the list of required works. The documentation provides for relocating the transformer substation and public restrooms, laying new utility networks, and constructing an additional columbarium wall for burials. In addition, changes affected the exterior and interior decoration of utility buildings, the boiler house, fencing structures, and general landscaping of the territory.
The project developers paid special attention to landscaping works: landscaping areas have changed, and the number of trees slated for removal during the expansion of the construction zone has increased. Despite increased funding and changes in the scope of work, the implementation timeline for this strategic project has faced further adjustments, sparking public debate regarding the transparency and efficiency of budget resource allocation.
"The agreement worth nearly UAH 879 million was concluded directly without an auction, raising numerous questions among regulatory bodies and local residents," industry experts note.
Source kyivschina24.com — kyivschina24.com/news/novyj-ministr-staryj-pidryadnyk-i-879-mln-bez-ten… ↗
Read next
Tragedy in Dymer: Death toll from Russian strike rises to eight
Rescuers have recovered the eighth body from the rubble of a destroyed building in Dymer, Kyiv region.
Clashes at Kyiv Pechersk Lavra: Police Launch Investigation
Clashes occurred at the Kyiv Pechersk Lavra between individuals with differing religious views. Law enforcement officers have documented the incident and are conducting a…
Civilian evacuation: ISW experts analyze proposals for humanitarian corridors
Analysts from the Institute for the Study of War (ISW) explained the differences between Ukraine's proposals for evacuations from the Kherson and Zaporizhzhia regions and…
💼EconomyAttack on Novoshakhtinsk Oil Refinery: Impact on Aggressor's Fuel Logistics in Rostov Region
On the night of November 23, the Novoshakhtinsk Oil Products Plant was targeted again, disrupting critical fuel supplies for the Russian military.
🧠AI AnalysisOil refinery attacked again in Rostov region
On the night of November 23, drones struck the Novoshakhtinsk oil refinery. The facility, which supplies fuel to the Russian army, sustained damage.
Police operation launched in Kharkiv following fatal shooting
On the evening of November 22, a man was killed in a shooting in Kharkiv. Law enforcement agencies have launched a special operation to apprehend the suspects.